Main parties to be procured
Possible project financiers are DBSA, GEF and the AfDB.
Project challenges
The major project challenge foreseen is timely sourcing of project finances.
Project documentation available
1.
City of Cape Town, 2010. Progress with Implementation of the Long‐term Water
Conservation and Water Demand Management Strategy, Assessment, Summary
Report, September 2010.
2.
MA Shepherd and VA Poona, undated. Reducing Non‐Revenue Water In The
Durban Central Business District.
3.
SADC Economic Accounting of Water Project Reports.
Intervention requiring financing
Project to be presented for grant financing during the planned 1st SADC Infrastructure
Investment Summit and Conference to be held in the last quarter of 2012.
Revenues for financing repayment
This is a capacity building project. Future benefits will manifest in efficient execution
of Water Sector projects in SADC.
Estimated total cost
It is estimated that it will cost US$1 million per city for the study giving a total cost
for all 15 cities of US$15 million.
Execution period
After project funding is secured in 2012, the project will be executed from 2013 and
be completed in 2014. Thereafter, the project’s recommendations for each will then
be implemented.