ECOWAS Tenders Code
2. The securities provided for under Part III, Chapter II of this Code may be replaced by
a joint and several guarantor whereby a third party undertakes to pay to the procuring
entity any sums owed by the supplier, contractor or service provider in respect of the
contract up to the amount posted as guarantee.
3. The joint and several guarantor shall be chosen from approved reputable banks / insurance
companies.
4. The joint and several guarantee shall be in a format specified by the procuring entity. The
form shall contain an undertaking to pay on first demand, any amount owed by the
contractor up to the amount guaranteed.
Article 70: Other Securities
1. Where the contract provides for advance payment, the supplier, contractor or service
provider, shall provide a security for the repayment of the advance payments. Advance
payment shall not exceed thirty (30) percent of the contract price.
2. If the contractor receives advance payments for the purchase of materials or goods, the
ownership of these materials is transferred to the procuring entity. The contractor shall be
legally responsible for the care of these materials.
3. Where the contract specifies a warranty period, a portion of each payment shall be
retained by the procuring entity as retention guarantee in order to secure the full
compliance with the contract obligations. The sum retained by the procuring entity as
determined by the Contracting Authority, which may be replaced by a joint and several
guarantee, should not exceed ten (10) percent of the total amount of the payments and
shall be specified in the conditions of contract depending on the contract value and risks. In
any case , the retention guarantee shall be entirely returned at the expiry of the guarantee
period. This period is the period during which the work is accepted and the facility
utilized during which any defects discovered shall be rectified by the contractor at no
liability to the contractor. The duration of the guarantee period shall be fixed in the contract.
4. The contract shall determine, where necessary, any guarantees other than those stipulated
above which may, under special circumstances, be required of the supplier or contractor to
ensure the discharge of his obligations. The contract shall define the rights of the
procuring entity in relation to such guarantees.
Chapter III: Modifications during the Execution of the Contract
Article 71: Modification in the Contract Quantities or Price
1. Any variations to the initial contract shall be embodied in an amendment to the contract
except in the cases specified in paragraphs (a) and (c) of this Article.
a) Variations in the execution of contracts for works, supplies or services not exceeding ten
percent (10%) of the total value of the contract shall be verified and approved by an order
issued by the procuring entity.
Final
Page 33