achieving consensus on the project with the project riparian states.
Project documentation available
To be identified.
Intervention requiring financing
Project to be presented for grant financing during the planned 1st SADC Infrastructure
Investment Summit and Conference to be held in the last quarter of 2012.
Revenues for financing repayment
This is a study that will end with data collection to facilitate the efficient management
of the SADC shared watercourses, as the riparian states will be better informed.
Future benefits will manifest in all the SADC shared watercourse riparian states.
Estimated total cost
The estimated total project costs are US$15 million.
Execution period
After project funding is secured in 2012 and the drafting of the ToR and procurement
of a consultant in 2013, the project will be executed from 2014 and be completed in
2016. Monitoring and data collection will continue thereafter.