3. THE PLAINTIFF’S CASE:
By an Application dated the 08th of December, 2015, the Plaintiff
brought an action against the Defendants for breach of contract and
failure of the Defendants to pay the Plaintiff the full sum stated in a
contract, after duly discharging its obligations thereunder.
The Plaintiff thus specifically averred that:
1. The 2nd Defendant represented by the 1st Defendant, by a
publication in specific papers, particularly The Guardian
Newspaper of June 12, 2014, invited bids for the production of
SAP infrastructure in three separate lots.
2. The Plaintiff indicated interest in Lots 1, 2, 3 and submitted its
bids after purchase of the bid documents.
3. Having satisfied the requirements of the bid, the Plaintiff was
awarded the contract for the supply, installation and maintenance
of power Associated Equipment by the Defendants.
4. The place for the supply installation and maintenance of power
and Associated Equipment was to be the 2nd Defendant’s
Headquarters in Abuja while the renovation of the ECOWAS Data
Recovery Centre (DRC) site was stated to be the ECOWAS
Commission Liaison Office, Lagos.
5