Southern Africa Development Community Secretariat – Procurement and Grants Policy
(a)
accountability of the Procuring Entity’s staff engaged in procurement activities, by defining
clear roles and responsibilities among the staff and organizational structures involved in the
procurement activities;
(b)
separation of duties between various department and functions within the Procuring Entity
organization, by ensuring that procurement responsibilities are cascaded among various
structures within the organization
(c)
quality control over the procurement activities, by ensuring that all procurement documents
sent for approval are subject to ex-ante control
(d)
absence of conflict of interest, by ensuring that the structure has adequate checks and balances
and no player is at the same time referee; and
(e)
efficiency in the implementation of procurement activities, by ensuring that the
implementation structure will not require unnecessary resources and/or promote redundant
processes that are costly and/or time consuming for the organization.
Article 46. Modifying contracts
(1)
(2)
Contracts may be subject to modification during implementation provided that the following
principles are observed:
(a)
Contract modifications shall be formalized through an administrative order or an addendum
to the contract in accordance with the provisions of the General Conditions of the Contract
and accepted by the contracting parties.
(b)
No modification to the contract may alter the award conditions prevailing at the time the
contract was awarded.
(c)
Any modification of the contract value shall not exceed an aggregate amount of up to twenty
five percent (25%) of the original contract amount.
(d)
Any modification of the duration of the contract shall not exceed an aggregate of maximum of
one hundred percent (100%) of the duration of the initial contract.
(e)
All modification shall be signed by contracting parties prior to the expiration of the contract.
(f)
All variations under this Article shall be approved by Tender Committee.
The procedures for initiating and approving any modification to the contract shall be detailed in the
Procurement Regulations.
Article 47. Monitoring and Auditing of Procurement Activities
(1)
The SADC Secretariat shall conduct regular Monitoring and Evaluation of the procurement
activities financed by the SADC Secretariat through its dedicated structure. This will include
contractors’ performance.
(2)
The Monitoring and Evaluation reports shall be presented at least once per year to the Executive
35