Project title
Lesotho Lowlands Water Supply Scheme – Zone 1 (Project P1‐4)
Project sponsors
The project proponent is the Lesotho Highlands Water Commission.
Participating countries
Lesotho
Objectives
To provide water supply services for Botha‐Bothe and adjacent villages in the north of
Lesotho.
Project description
The project will supply Botha Bothe and adjacent villages with domestic water. The
project is designed in such a way that treated water will be delivered to bulk storage
reservoirs from where the settlements will be supplied. The strategic storage will
provide reliability during system repairs and power outages. Future expansions are
provided for in the design of the project. Where possible, the expansion will be
through modular design, e.g. twining storage, modular treatment works and pumping
stations. In essence, the facilities can be easily upgraded by adding more components.
The existing infrastructure will be integrated, where appropriate or possible, but
where the systems are very small or old/unreliable, these will be superseded by the
project infrastructure. The infrastructure to be developed will provide water for
drinking and sanitation to Botha‐Bothe and adjacent villages. This is planned to
benefit a total of 127 000 people by 2027. Ensuing from the project will be socio‐
economic and health benefits to the target population in the area. The project will
also ease the water demand pressures from the industrial firms in Botha Bothe, with
the additional employment further benefitting the town’s population.
It is estimated that the total surface water storage to be created for this project will be
6
3
100 x 10 m .
The project is designed around five standardised components:
Expected results
River intakes to abstract raw water from the Hololo River;
Water treatment plant to convert the raw water into potable water;
Pipeline to transport the potable water to the demand centres;
Pumping station to lift the potable water to the demand centres; and
Bulk reservoir storages at strategic locations.
The infrastructure to be developed will provide water for drinking and sanitation to
Botha‐Bothe and adjacent villages. This is planned to benefit a total of 106 800 people
to the year 2020. Ensuing from the project will be socio‐economic and health benefits
to the target population in the area.��The project will also ease the demand pressures
from the industrial firms in town, with the employment benefits further ensuing to
the town’s population.
Ongoing related activities in the Similar efforts in other SADC Member States pursuant to meeting the MDG targets on
region
water supply and sanitation services.
Description of national plan to the The feasibility study and the preliminary designs of the whole Low Lands Water
project
Scheme were completed in September 2004. The institutional and policy framework
were completed in February 2007 with finalisation of the Lesotho Water and
Sanitation Policy. The legal and regulatory frameworks were finalised in 2008 with the
passing of the Lesotho Water Act of 2008, the Lesotho Electricity and Water Authority
of 2008, and the Water and Sewerage Authority Vesting Bill of 2008. The relevant
government departments have approved detailed design drawings and the tender
dossiers of all the eight zones of the Low Lands Bulk Water Supply Project. While
Zones 4 and 5 of the Low Lands Water Scheme is under way, the other zones are
complete from the proposal view and awaiting funding.
Status
The project can be considered to be in Phase 5 of the ICA Project Development
114