Project title
Lubango Phase II Water Supply and Sanitation Project (Project P1‐1)
Project sponsors
The project proponent is the Ministry of Energy and Water in Angola.
Participating countries
Angola
Objectives
The principal purpose of this project is to rehabilitate and extend the water supply
and sanitation system of the City of Lubango, considered the second largest city in
Angola.
Project description
The urgent reconstruction works for water supply and sanitation are needed as a basic
requirement for the development of the city and surrounding areas. The project will
supply 70 litres/person/day of domestic water supply to a total of 1 200 000 residents
of Lubango. The project construction activities include:
Rehabilitation of all components of water supply;
Drilling of an additional borehole at Nossa Senhora do Monte Wellfield;
Construction of a water reservoir at Esplanada da Capela; and
Installation of 15 km of sewer interceptors for the sanitation network.
The project will be complemented by a monitoring project for the development of
groundwater in the Tundavala mountains.
Expected results
The benefit from the implementation would be significant to the population in
general. Improvement of the system will bring industrial growth and increase wealth
to the population, particularly with regard to the growth of agro‐food and others
industries with associated increase in employment opportunities. The tourism
industry is growing rapidly.
Ongoing related activities in the Similar efforts in other SADC Member States pursuant to meeting the MDG targets on
region
water supply and sanitation services.
Description of national plan to the Phase 1 of this project was launched in March 2011. The German company, Gauff
project
Engineering, is doing the management of the Phase 1 project and will assist in
finalising requirements for Phase 2.
Status
The project can be considered to be in Phase 3 of the ICA Project Development
Phases.
Next steps
Feasibility studies for Lubango Phase II project should commence in 2012 and be
completed by 2013. Detailed designs and tendering for construction will be done in
2014. Implementation and construction of the associated project components is
expected to start in 2015 and will be completed by 2016.
Business model
Investment project financed as a BOT, grants or from loans.
Main parties in place
Ministries responsible for water and sanitation in the participating countries.
Main parties to be procured
Possible project financier is the German credit agency, Ausfurkredltgeschaft.
Project challenges
The major project challenge is the timely sourcing of project finances.
Project documentation available
1.
Investment programme for Ministry of Energy and Water until 2016, projecto
Reabilitaçãoe Reforço do sistema de Abastecimento de Água da cidade do
Lubango (Phase 1). Page 13 (Phase 1 details only).
2.
28 February 2011. Novo sistema dedistribuição garante mais água ao Lubango.
Jornal de Angola. (Phase 1 only)
3.
SADC. RSWIDP part 2 final report. June 2006. (Historical perspective)
4.
Council of ministers approves GAUFF‐project in Lubango.
http://www.gauff.net/en/news/articles/article/ministerrat‐von‐angola‐
genehmigt‐gauffprojekt‐in‐lubango.html. Last accessed August 2011.
2011.