ECOWAS Tenders Code
b) Where the variation in the quantity of the works, supplies or services exceeds 10 percent but
is less than or equal to twenty five percent (25%) of the basic contract value, such variation
shall be the subject of an amendment to the contract.
c) Where the totality of the variation in the quantity of the works, supplies or services
exceeds twenty five percent (25%) of the contract value calculated on the basis of initial
costing, a new contract shall be drawn up using the same procedure as for the initial
contract.
d) The total amount granted by virtue of amendments in respect of a single contract shall
not exceed twenty five percent (25%) of the initial contract value.
e) Price reviews in compliance with contractual terms shall not justify the introduction of
amendments to the contract.
2. Additional clauses shall be drawn up and approved under same terms as the initial
contract.
3. No additional clauses shall be added after final delivery of the goods and services.
Chapter IV: Payments in Public Contracts
Article 72: Advance Payments Progress and Final Payments
Suppliers, contractors and service providers are entitled to advance payments and progress
payments in accordance with the provisions set forth below. Each contract shall specify the
administrative and technical conditions governing the payment of the advances or progress
payments referred to in this chapter.
Article 73: Advance Payments
1. Advance payments may be made under the contract. The total amount of these advance
payments may not, in any case, exceed thirty (30) percent of the initial price of the
contract for works, goods and services and intellectual services.
2. Advance payments and their terms of payment must be specified in the bidding documents
or request for proposals. Whatever the amount is, they should be fully secured by a bank /
insurance guarantee, or a joint and several guarantee. For intellectual services, this
guarantee is not required if the advance payment is limited to a maximum of Ten (10) per
cent of the total contract price.
3. Advance payments are reimbursed according to a fixed rate specified in the contract, by
deduction from the sums due to the supplier, contractor or service provider, and in any
event before the end of the contract. In the case of a total or partial termination of the contract,
the procuring entity has the right, without prejudice to other outstanding payments, to demand
immediate refund of outstanding advances.
4. If preparatory operations for construction or supply of goods or services require prior
commitment of funds, advance payments may be made to the contractor to carry out these
operations. The cause, the amount and the terms of payment of such advances shall be
stated in the special conditions of contract for each individual contract.
Final
Page 34